BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVEInfraLens App·Free on Play Store, offline-readyNEW
PMC📐 Design CoordinationGFC Submission Tracker

GFC Submission Tracker

log
PMC-DES-LOG-002·v1.0-beta·⚠ Beta — review before use

Tracks GFC (Good for Construction) drawing submissions + approvals — by discipline, by area, by date. Critical to identify GFC bottlenecks that delay construction.

ReferencesFIDIC Sub-clause 5.2 (Contractor's Documents)ISO 19650 (BIM CDE)Project Document Control Procedure
Download
📍 When to use this template
  • Weekly tracking by design office + PMC.
  • Pre-NTP audit + verification.
  • Delay claim documentation (per FIDIC 8.4).
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Tracker Header4 fields
Project Reference
_____________
Status as of Date
_____________
Updated By
_____________
Total Drawings (Planned vs Issued)
_____________
2GFC Status by Discipline8 fields
Discipline
_____________
Total Drawings Planned
_____________
Issued Latest Revision
_____________
Pending GFC Status
_____________
Critical Path Impact
_____________
Target GFC Date
_____________
Designer Owner
_____________
Remarks
_____________
3Discipline-wise Detail (per Drawing)6 fields
Drawing Number
_____________
Title + Description
_____________
Submission Status
_____________
Revision
_____________
GFC Date (Issued / Pending)
_____________
Comments / Resubmission Required
_____________
4Issues + Escalation4 fields
Drawings Pending > 30 days
_____________
Critical Activity Affected
_____________
Escalation Status
_____________
Resolution Target
_____________
💡 Sample filled excerpt
12-May-2026. Total Planned: 245 drawings. GFC Issued: 168 (69 %). Pending: 77. By Discipline: Civil 95 % done, Struct 80 %, MEP 55 % (delayed by HVAC sub-consultant). Critical path: Foundation drawings 100 % done; MEP for L3 onwards critical. Escalation: HVAC consultant — target 30-May.
⚖ Compliance notes
  • Per FIDIC Sub-clause 5.2, designer's documents (GFC) must be issued per agreed schedule.
  • Delay in GFC issuance attributable to consultant / client = extension of time for contractor (Sub-clause 8.4).
  • Critical path GFC delay = project delay; closely tracked + escalated.
  • Construction without GFC = unauthorized work; rework risk.

Engineer's Notes — GFC Submission Tracker

Why the GFC Submission Tracker matters

GFC (Good for Construction) is the final design-cycle milestone — the designer formally releases the drawing for actual site execution. Only GFC-stamped drawings can be built from; non-GFC drawings are advisory only.

The GFC Submission Tracker is the project-level master log of which drawings have achieved GFC status, which are still in review, and which are pending revision. For projects with 500-5,000 drawings, this tracker is essential — without it, the project manager doesn't know what's ready for construction vs what's blocked.

Cost of getting GFC wrong: building from non-GFC drawings = demolition + rework when GFC version is finally issued; costs typically 5-15× the original construction cost for the affected element.

How the tracker operates

Per-drawing entry: - Drawing reference number - Discipline (architectural / structural / MEP / plumbing) - Current revision - Status: In Design / In Review / GFC Issued / Superseded - GFC date - Construction status - Notes

Updated weekly during design phase; daily during peak transition from design to construction.

Color-coded dashboard view: - 🔴 Red: not yet GFC — site cannot proceed - 🟡 Yellow: in final review - 🟢 Green: GFC issued + construction can begin - ⚫ Grey: GFC issued + construction complete

Project manager + PMC + main contractor review weekly. Discrepancies between expected GFC date vs actual cause schedule slippage; tracker visibility forces designer accountability.

Common GFC issues

1. GFC stamp without all approvals — designer issues GFC before all consultants (structural / MEP / architect) have signed off. Construction begins; later coordination issue forces drawing recall.

2. Missed dependencies — Drawing A waits on input from Drawing B; B not GFC'd; A delayed. Tracker should map dependencies.

3. GFC date slippage — designers consistently miss GFC dates → construction schedule slips. Tracker provides early warning.

4. Wrong revision marked GFC — older revision stamped GFC while newer revision exists. Strict revision-control discipline at the GFC step.

5. GFC release without GFC stamp — drawing emailed without proper stamp marking; contractor builds anyway; dispute over which revision was the basis.

6. No GFC withdrawal protocol — when design defect discovered post-GFC, formal withdrawal + reissue protocol is needed. Sometimes ignored.

Cross-references

Companion PMC formats: - Drawing Transmittal (PMC-DES-FRM-001) — formal document transmission - Design Review Register (PMC-DES-REG-001) — review iterations leading up to GFC - Clash Detection Report (PMC-DES-RPT-001) — coordination output (must close before GFC) - BIM Coordination Log (PMC-DES-LOG-001) — BIM-based coordination decisions

Standards: ISO 19650 Parts 1-5 (BIM information management); PAS 1192-2 (design + delivery phase); ISO 9001:2015 Clause 8.3 (design and development control).