BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEW→BidEasy·Government tenders, searchableLIVE→InfraLens App·Free on Play Store, offline-readyNEW→
PMCβ€ΊπŸ“ Design Coordinationβ€ΊDesign Change Request (DCR)

Design Change Request (DCR)

form
PMC-DES-FRM-002Β·v1.0-beta·⚠ Beta β€” review before use

Formal request to modify design after GFC. Tracks scope, cost, schedule + quality implications. Required for any design change after GFC issuance.

ReferencesFIDIC Sub-clause 13.1 (Variations)CPWD Works Manual 2019Project-specific Change Management ProcedureISO 9001:2015 (Quality Management)
Download
πŸ“ When to use this template
  • Any change to GFC drawings or specifications.
  • Client-initiated scope change.
  • Contractor-discovered design issue requiring modification.
  • Statutory authority requirement change.
  • Material substitution proposal.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Request Header6 fields
DCR Number
_____________
Date of Request
_____________
Requesting Party (Client / Contractor / PMC)
_____________
Affected Drawing(s)
_____________
Affected Element / Location
_____________
Priority (Urgent / High / Medium / Low)
_____________
2Change Description4 fields
Current Design (As per GFC)
_____________
Proposed Change
_____________
Reason for Change
_____________
Supporting Drawings / Calculations Attached
_____________
3Impact Assessment6 fields
Cost Impact (β‚Ή + Sign +/-)
_____________
Schedule Impact (Days + Sign +/-)
_____________
Quality Impact (Better / Equal / Lower)
_____________
Safety Impact
_____________
Affected Trades / Disciplines
_____________
Other Approvals Required
_____________
4Approval Chain5 fields
Designer Review + Approval
_____________
PMC / Engineer Review
_____________
Client / Owner Approval (where required)
_____________
Final Approval Date
_____________
Revised GFC Drawing Reference
_____________
5Implementation4 fields
Revised GFC Issue Date
_____________
Variation Order Reference (if applicable)
_____________
Construction Start with Change
_____________
Verification + Sign-off Post-implementation
_____________
πŸ’‘ Sample filled excerpt
DCR #2026-23, 14-May-2026. Affected: STR-FL-04 (slab L+4). Current: 200 mm RCC. Change: 250 mm RCC + increase rebar for added crane load. Impact: +β‚Ή3.5 lakh, +4 days. Approval: 18-May-2026. Revised GFC: STR-FL-04 Rev 4. VO #38 issued.
βš– Compliance notes
  • Per FIDIC Sub-clause 13.1, design changes that increase scope = Variations (require Variation Order + payment).
  • Design changes initiated by contractor that aren't scope additions = no extra payment unless approved.
  • Schedule impact assessment is critical input for EOT (Extension of Time) claims under Sub-clause 8.4.
  • Statutory authority changes may attract specific procedure under contract.
  • Closure of DCR + sign-off after implementation verification is mandatory.

Engineer's Notes β€” Design Change Request (DCR)

Why the Design Change Request matters

On any construction project, GFC (Good For Construction) drawings are not the end of design β€” they are the beginning of construction. Changes happen: client wants a different layout, contractor discovers a site condition that breaks the design, statutory authority adds a requirement, material market changes force substitution, structural review reveals a missed load.

Without a formal Design Change Request (DCR) process, these changes get implemented informally: - Verbal instruction β†’ construction β†’ later disputes on payment, schedule, quality - Multiple parties making conflicting changes β†’ coordination failures - No traceability between current GFC and what was actually built - Variation claims rejected because no contemporaneous record of approval - As-built drawings drift from design drawings; FM nightmare at handover

The DCR system provides: - Single channel for change proposals (any party can initiate) - Impact assessment before implementation (cost / schedule / quality / safety) - Approval chain with signed-off authority - Variation Order linkage (for paid changes) - Revised drawing issuance after approval - Audit trail for arbitration / claim defence

Governed by FIDIC Sub-clause 13 (Variations), CPWD Works Manual + project-specific change management procedure under ISO 9001:2015 Clause 8.5.6 (Control of changes).

How a DCR moves through the system

Standard workflow (typically 5-14 days for routine, 24-72 hours for urgent):

Step 1 β€” Initiation: - Initiator party (Client / Contractor / PMC / Consultant / Authority) raises DCR - DCR number assigned (sequential per project, e.g., DCR-2026-035) - Current design described (with GFC drawing references) - Proposed change described (sketch + calculations attached) - Reason for change - Priority (Urgent / High / Medium / Low)

Step 2 β€” Designer review: - Lead architect / structural / MEP designer reviews (depending on which discipline) - Verifies technical feasibility - Recommends acceptance / modification / rejection - Issues revised design / sketches if accepted

Step 3 β€” Impact assessment: - Cost impact (positive / negative + amount) - Schedule impact (days + critical path effect) - Quality impact (better / equal / lower performance) - Safety impact (especially for structural / fire / electrical changes) - Affected trades / disciplines - Other approvals required (statutory, lender, end-user)

Step 4 β€” Commercial review: - Contractor's rate analysis for variation pricing - PMC / Engineer's review of cost reasonableness - Client / Owner approval if cost / schedule exceeds delegation limits

Step 5 β€” Formal approval: - Final approval by designated authority (typically Owner's PM up to delegation, Director / Board above) - Variation Order issued (linking to DCR) - Revised GFC drawing issued (with revision number) - Construction permitted with revised design only

Step 6 β€” Implementation + closure: - Construction per revised design - Site verification + sign-off - DCR closed in system - Cross-referenced in as-built drawings + project records

Categorisation for governance: - Type 1: Minor (< β‚Ή5 lakh, no schedule impact, single discipline) β€” PM-level - Type 2: Moderate (β‚Ή5-25 lakh, < 7 days schedule, 1-2 disciplines) β€” PMC + Client PM - Type 3: Major (> β‚Ή25 lakh OR > 7 days OR cross-discipline) β€” Steering Committee / Board

Common DCR process failures

1. Informal verbal changes β€” work executed without DCR; payment disputed; rework if not accepted.

2. No impact assessment β€” DCR approved without cost / schedule numbers; later disputes on actual impact.

3. Scope creep β€” cumulative small DCRs add up to major scope change; no aggregate review; cost overrun discovered late.

4. Designer not consulted β€” change approved by PMC without designer; technical issues surface post-construction.

5. Statutory implications missed β€” change affects fire / structural / accessibility code; statutory authority objects at OC stage.

6. Variation pricing disputes β€” DCR approved but rate not agreed; later rate-only arbitration on each DCR.

7. Revised drawings not issued β€” change approved verbally but no Rev drawing; field drawings still show old design; confusion on site.

8. Schedule float consumed silently β€” minor DCRs eat 1-2 days each; cumulative 30-day slip with no EOT claim filed; contractor takes the hit.

9. Quality reduction passed β€” material substitution approved on cost; equivalent quality not verified; later defects.

10. DCR not closed β€” implementation done but DCR remains open in register; audit gap; can't archive.

11. No traceability to PR / RFI β€” change driven by RFI but not linked; later, why-was-this-changed question can't be answered.

12. Multiple revisions on same DCR β€” design keeps changing; should have been multiple DCRs; tracking becomes impossible.

Cross-references

Companion PMC formats: - Design Review Register (PMC-DES-REG-001) β€” overall design review - Drawing Transmittal (PMC-DES-FRM-001) β€” drawing release tracking - GFC Submission Tracker (PMC-DES-LOG-002) - Variation Order Register β€” VO tracking - RFI Register β€” Request for Information - Claim Log (PMC-RSK-LOG-003) β€” for variation-related claims - Drawing Register β€” master drawing list

Standards + contracts: - FIDIC Red / Yellow / Silver Book 1999 + 2017 β€” Sub-clause 13 (Variations + Adjustments) - CPWD Works Manual 2019 β€” Chapter 8 (Variations) - ISO 9001:2015 Clause 8.5.6 β€” Control of changes - ISO 19650 β€” Information management in BIM context (drawing version control) - NHAI / MoRT&H Manuals β€” Variation procedures for highway works - PMI PMBOK 7th Edition β€” Integrated change control