Formal request to modify design after GFC. Tracks scope, cost, schedule + quality implications. Required for any design change after GFC issuance.
DCR #2026-23, 14-May-2026. Affected: STR-FL-04 (slab L+4). Current: 200 mm RCC. Change: 250 mm RCC + increase rebar for added crane load. Impact: +βΉ3.5 lakh, +4 days. Approval: 18-May-2026. Revised GFC: STR-FL-04 Rev 4. VO #38 issued.
On any construction project, GFC (Good For Construction) drawings are not the end of design β they are the beginning of construction. Changes happen: client wants a different layout, contractor discovers a site condition that breaks the design, statutory authority adds a requirement, material market changes force substitution, structural review reveals a missed load.
Without a formal Design Change Request (DCR) process, these changes get implemented informally: - Verbal instruction β construction β later disputes on payment, schedule, quality - Multiple parties making conflicting changes β coordination failures - No traceability between current GFC and what was actually built - Variation claims rejected because no contemporaneous record of approval - As-built drawings drift from design drawings; FM nightmare at handover
The DCR system provides: - Single channel for change proposals (any party can initiate) - Impact assessment before implementation (cost / schedule / quality / safety) - Approval chain with signed-off authority - Variation Order linkage (for paid changes) - Revised drawing issuance after approval - Audit trail for arbitration / claim defence
Governed by FIDIC Sub-clause 13 (Variations), CPWD Works Manual + project-specific change management procedure under ISO 9001:2015 Clause 8.5.6 (Control of changes).
Standard workflow (typically 5-14 days for routine, 24-72 hours for urgent):
Step 1 β Initiation: - Initiator party (Client / Contractor / PMC / Consultant / Authority) raises DCR - DCR number assigned (sequential per project, e.g., DCR-2026-035) - Current design described (with GFC drawing references) - Proposed change described (sketch + calculations attached) - Reason for change - Priority (Urgent / High / Medium / Low)
Step 2 β Designer review: - Lead architect / structural / MEP designer reviews (depending on which discipline) - Verifies technical feasibility - Recommends acceptance / modification / rejection - Issues revised design / sketches if accepted
Step 3 β Impact assessment: - Cost impact (positive / negative + amount) - Schedule impact (days + critical path effect) - Quality impact (better / equal / lower performance) - Safety impact (especially for structural / fire / electrical changes) - Affected trades / disciplines - Other approvals required (statutory, lender, end-user)
Step 4 β Commercial review: - Contractor's rate analysis for variation pricing - PMC / Engineer's review of cost reasonableness - Client / Owner approval if cost / schedule exceeds delegation limits
Step 5 β Formal approval: - Final approval by designated authority (typically Owner's PM up to delegation, Director / Board above) - Variation Order issued (linking to DCR) - Revised GFC drawing issued (with revision number) - Construction permitted with revised design only
Step 6 β Implementation + closure: - Construction per revised design - Site verification + sign-off - DCR closed in system - Cross-referenced in as-built drawings + project records
Categorisation for governance: - Type 1: Minor (< βΉ5 lakh, no schedule impact, single discipline) β PM-level - Type 2: Moderate (βΉ5-25 lakh, < 7 days schedule, 1-2 disciplines) β PMC + Client PM - Type 3: Major (> βΉ25 lakh OR > 7 days OR cross-discipline) β Steering Committee / Board
1. Informal verbal changes β work executed without DCR; payment disputed; rework if not accepted.
2. No impact assessment β DCR approved without cost / schedule numbers; later disputes on actual impact.
3. Scope creep β cumulative small DCRs add up to major scope change; no aggregate review; cost overrun discovered late.
4. Designer not consulted β change approved by PMC without designer; technical issues surface post-construction.
5. Statutory implications missed β change affects fire / structural / accessibility code; statutory authority objects at OC stage.
6. Variation pricing disputes β DCR approved but rate not agreed; later rate-only arbitration on each DCR.
7. Revised drawings not issued β change approved verbally but no Rev drawing; field drawings still show old design; confusion on site.
8. Schedule float consumed silently β minor DCRs eat 1-2 days each; cumulative 30-day slip with no EOT claim filed; contractor takes the hit.
9. Quality reduction passed β material substitution approved on cost; equivalent quality not verified; later defects.
10. DCR not closed β implementation done but DCR remains open in register; audit gap; can't archive.
11. No traceability to PR / RFI β change driven by RFI but not linked; later, why-was-this-changed question can't be answered.
12. Multiple revisions on same DCR β design keeps changing; should have been multiple DCRs; tracking becomes impossible.
Companion PMC formats: - Design Review Register (PMC-DES-REG-001) β overall design review - Drawing Transmittal (PMC-DES-FRM-001) β drawing release tracking - GFC Submission Tracker (PMC-DES-LOG-002) - Variation Order Register β VO tracking - RFI Register β Request for Information - Claim Log (PMC-RSK-LOG-003) β for variation-related claims - Drawing Register β master drawing list
Standards + contracts: - FIDIC Red / Yellow / Silver Book 1999 + 2017 β Sub-clause 13 (Variations + Adjustments) - CPWD Works Manual 2019 β Chapter 8 (Variations) - ISO 9001:2015 Clause 8.5.6 β Control of changes - ISO 19650 β Information management in BIM context (drawing version control) - NHAI / MoRT&H Manuals β Variation procedures for highway works - PMI PMBOK 7th Edition β Integrated change control