BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVEInfraLens App·Free on Play Store, offline-readyNEW
Formats  › Estimation & Rate Analysis  › Rate Analysis —
Form · FMT-EST-004

Rate Analysis — Plaster (Internal 1:4)

8 fields across 2 sections. Internal plaster 1:4 — most common; external 1:6 has separate analysis.
8 Fields
2 Sections
Per tender
Estimator, QS

Format Preview

S.No.Field / CheckpointReferenceStatus
A. INPUT QUANTITIES (per 1 m² 12mm plaster)
A1Mortar 1:4 — 0.014 m³
Acceptance: Per CPWD
Cement 4.4 kg + Sand 0.012 m³
OK
NC
NA
A2Cement — 4.4 kg (0.088 bag)
Acceptance: Per spec
Per analysis
OK
NC
NA
A3Sand (fine) — 0.012 m³
Acceptance: Per spec
Per IS 1542
OK
NC
NA
A4Water — 5 L
Acceptance: Drinkable
Per workability
OK
NC
NA
A5Labour — Mason 0.18 day + Mazdoor 0.45 day
Acceptance: Productivity
Per CPWD
OK
NC
NA
A6Scaffolding hire (if > 2.5m) — 5% extra
Acceptance: Per height
Per CPWD
OK
NC
NA
B. RATES + COSTS
B1Material + labour × rates = direct cost / m²
Acceptance: Computed
Latest market
OK
NC
NA
B2OH + Profit + quoted rate
Acceptance: Computed
Per company
OK
NC
NA
A. INPUT QUANTITIES (per 1 m² 12mm plaster)
A1Mortar 1:4 — 0.014 m³
Cement 4.4 kg + Sand 0.012 m³
Per CPWD
OKNCNA
A2Cement — 4.4 kg (0.088 bag)
Per analysis
Per spec
OKNCNA
A3Sand (fine) — 0.012 m³
Per IS 1542
Per spec
OKNCNA
A4Water — 5 L
Per workability
Drinkable
OKNCNA
A5Labour — Mason 0.18 day + Mazdoor 0.45 day
Per CPWD
Productivity
OKNCNA
A6Scaffolding hire (if > 2.5m) — 5% extra
Per CPWD
Per height
OKNCNA
B. RATES + COSTS
B1Material + labour × rates = direct cost / m²
Latest market
Computed
OKNCNA
B2OH + Profit + quoted rate
Per company
Computed
OKNCNA
Approval / Sign-Off
APPROVED
HOLD — REVISIONS REQUIRED
REJECTED
Overall Verdict
Name / Sign / Date
Prepared By — Name / Sign
Name / Sign / Date
Reviewed By — Name / Sign
Name / Sign / Date
Approved By — Name / Sign
Name / Sign / Date
Date & Time
Name / Sign / Date
Remarks
Name / Sign / Date

Engineer's Notes — Rate Analysis — Plaster (Internal 1:4)

Why the Internal Plaster Rate Analysis matters

Internal plaster (cement-sand 1:4) is the richer mix vs external 1:6 — providing smoother surface, better adhesion, and improved durability for indoor wall finishing. This rate analysis builds up the unit rate (per m²) for tender pricing, claim defense, and variation order rates.

Key difference from 1:6 external: more cement (higher cost) but better workability + finish, less sand wastage, faster productivity (smoother substrate), higher labour skill required.

Cost build-up — per 10 m² of 1:4 plaster, 12-15 mm thick

Materials: - Cement: ~85 kg — at ₹400-450/bag of 50 kg = ₹680-770 - Sand: ~0.14 m³ — at ₹1,500-2,500/m³ = ₹210-350 - Water: ~20-25 L — negligible cost - Materials sub-total: ₹890-1,120

Labour (premium internal finishing): - Mason: 0.6-0.8 day @ ₹650-950/day = ₹390-760 - Helper: 0.6-0.8 day @ ₹450-650/day = ₹270-520 - Labour sub-total: ₹660-1,280

Other: scaffolding ₹50-150; curing ₹50-100; wastage (5%) ₹50-80; overhead (10-15%) ₹150-250; profit (10-15%) ₹150-250.

Total: ₹2,000-3,230 per 10 m²₹200-323 per m².

Note: 1:4 internal is approximately ₹50-80/m² LESS than 1:6 external because internal doesn't need scaffolding for ground floor + works are faster + less wastage. But cement cost is higher.

Internal vs external plaster choices

Internal plaster (1:4): - Use for visible interior walls of homes, offices, hotels, hospitals - Premium finish — accepts paint, wallpaper, decorative finishes - Thinner application (12-15 mm) — saves material + reduces dead load - Easier to repair / patch later - Better adhesion for tile / cladding fixed later

External plaster (1:6): - Use for exterior walls + courtyard walls - More water-resistant (denser mortar with less voids) - Thicker application (15-20 mm) — better weather resistance - Cheaper per m² (less cement) - Better for paint adhesion + weathering

Specialty mixes: 1:3 (very rich) for highly visible surfaces; 1:5 (medium) compromise mix; 1:8 (lean) for low-cost / non-visible areas / scratch coat; 1:1:6 lime-cement for traditional / heritage / breathable finishes.

Cross-references

Companion formats: - Rate Analysis Plaster External 1:6 (FMT-EST-005) — external plaster - Rate Analysis Brickwork (FMT-EST-003) — masonry - Labour Productivity Sheet (FMT-EST-007) — per-trade productivity - Rate Analysis Shuttering (FMT-EST-006) — formwork costs

Codes / specifications: - CPWD Specifications 2019 — Volume 1 Section 13 (Plastering) - IS 1542:1992 — Sand for plaster - IS 2250:1981 — Code of Practice for Preparation and Use of Masonry Mortars - IS 269:2015 — OPC 33 cement - IS 1200 Part 12:1976 — Method of measurement

More related