ESTIMATION

Liquidated Damages (LD)

Pre-agreed sum deducted per period of contractor delay beyond completion date

Also calledliquidated damagesLDdelay damagespenalty for delaycompensation for delay
Definition

Liquidated Damages (LD) is a sum, fixed in the contract in advance, that the contractor must pay (usually deducted from running bills) for each day/week of delay in completing the works beyond the contractual completion date (as extended by any granted Extension of Time). Being a genuine pre-estimate of the employer's likely loss from late completion, it spares the employer from having to prove actual damages โ€” distinguishing it from a true 'penalty', which Indian courts (Section 74, Indian Contract Act) will not enforce beyond reasonable compensation.

LD is typically expressed as a percentage of contract value per week (e.g. 0.5-1% per week) capped at an overall maximum (commonly 5-10% of contract value). It applies only to culpable contractor delay โ€” Extension of Time for employer-caused or excepted-risk delays must first be assessed, otherwise the LD clause can become unenforceable. LD recovery, EoT and delay analysis are among the most litigated areas of construction contracts.

Where used
  • Recovery for contractor delay from running bills
  • Extension-of-Time + delay-analysis assessment
  • Tender + contract risk pricing
  • Construction-claim + arbitration disputes
  • Programme + milestone management
Acceptance / threshold
Per the contract LD clause (e.g. % of contract value per week, capped overall). Enforceable as a genuine pre-estimate of loss (Indian Contract Act Sec 74); applies only to culpable delay after EoT is fairly determined.
Frequently asked
What is the difference between liquidated damages and a penalty?
Liquidated damages are a genuine pre-estimate of the employer's likely loss agreed in advance and recoverable without proving actual loss. A penalty is a sum out of proportion to likely loss; Indian courts (Sec 74) limit recovery to reasonable compensation.
Is there usually a cap on liquidated damages?
Yes โ€” most contracts cap total LD at a maximum percentage of the contract value (commonly 5-10%), with a per-week rate (e.g. 0.5-1%) applied to the period of culpable delay.
Related terms