QA/QC  › Concrete & RCC  › RCC Work Method
Form · QC-CON-FRM-002

RCC Work Method Statement

46 checkpoints across 8 sections.
46 Checkpoints
8 Sections
As needed
Site Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. A. SCOPE OF WORK
A1Description of RCC Work
Acceptance: Clear narrative covering nature of work, extent, and project phase
Detailed description of concrete work scope
A2Location / Structural Elements Covered
Acceptance: List with reference to drawing numbers; include all elements in this work package
Identification of elements (slabs, beams, columns, footings, etc.) and zones
A3Estimated Volume (m³)
Acceptance: Calculated from drawings; used for material planning and sampling frequency
Total volume of concrete planned for this work
A4Duration / Schedule
Acceptance: From project schedule; phased if required
Planned start and completion dates
B. B. REFERENCE DOCUMENTS
B1Applicable IS Codes
Acceptance: IS 456:2000, IS 10262:2009, IS 383:1970 (Coarse and Fine Aggregate), IS 1786:2008, IS 516:1959, IS 1199:1959, IS 1498:1970 (Steel), IS 4031:1988 (Cement Testing)
List of all relevant Indian Standards for concrete work
B2Approved Drawings List
Acceptance: List drawing nos. and latest approved revisions
Reference drawing numbers with revisions
B3Approved Mix Design
Acceptance: Document ID, grade, w/c ratio, slump, cement type, approval date and approver signature
Reference to approved IS 10262 mix design document
B4Project Specification
Acceptance: Grade, exposure class, durability requirements, special requirements (if any)
Concrete specification from project contract/design doc
C. C. MATERIALS
C1Cement - Type and Grade
Acceptance: Grade 43/53; source and Mill Test Certificate (MTC) records maintained
Type of cement (OPC/PPC/PSC) and grade per IS 269/455/1489
C2Cement Storage Requirements
Acceptance: In covered store; max 10 bags high; on raised platform; FIFO rotation; shelf life 3 months max from date of packing; stock rotation recorded
Storage conditions per IS 456 Cl. 5.2
C3Fine Aggregate (Sand) - Source and Grading
Acceptance: Grading Zone II or III; natural or manufactured sand; silt content ≤3% (for fine sand) or ≤5% (coarse sand); testing per IS 2386:1963 Part I
Source and compliance with IS 383:1970 grading zone
C4Coarse Aggregate (Stone/Gravel) - Source and Grading
Acceptance: 20mm nominal size typical; flakiness index ≤30%; elongation index ≤30%; testing per IS 2386:1963 Part I; all sizes tested before batching commenced
Source and compliance with IS 383:1970 grading
C5Aggregate Testing Frequency
Acceptance: Sieve analysis every 500 tonnes; silt/moisture every 100 tonnes; flakiness/elongation every 1000 tonnes; records maintained with dates
Schedule for regular testing of aggregates
C6Reinforcement Steel - Grade and Type
Acceptance: Grade Fe 500D (primary); diameter per drawings; Mill Certificates (MC) obtained; traceability maintained
Steel grade per IS 1786:2008 (High strength deformed bars)
C7Steel Storage and Protection
Acceptance: On raised platform (min 300mm height); covered from rain; inspect for rust/damage before use; oiled if stored >6 months; bending at site tested per IS 1608:1995 (bend/rebend test)
Storage conditions for reinforcement steel
C8Water Quality
Acceptance: Potable water; pH 6-8; salt content <500 mg/litre; chloride <200 mg/litre; sulphate <200 mg/litre; testing done before use
Water used in concrete mix per IS 456 Cl. 5.4
C9Admixtures - Type and Dosage
Acceptance: Type (plasticizer/retarder/accelerator/air-entraining); dosage in mL/100kg cement or % by mass; approved mix design reference; batch testing if new source
Chemical admixtures per IS 9103:1999 and approved mix design
Showing 17 of 46 checkpoints ·
A. A. SCOPE OF WORK
A1Description of RCC Work
Detailed description of concrete work scope (IS 456:2000)
Clear narrative covering nature of work, extent, and project phase
A2Location / Structural Elements Covered
Identification of elements (slabs, beams, columns, footings, etc.) and zones (IS 456:2000)
List with reference to drawing numbers; include all elements in this work package
A3Estimated Volume (m³)
Total volume of concrete planned for this work (IS 456:2000)
Calculated from drawings; used for material planning and sampling frequency
A4Duration / Schedule
Planned start and completion dates (IS 456:2000)
From project schedule; phased if required
B. B. REFERENCE DOCUMENTS
B1Applicable IS Codes
List of all relevant Indian Standards for concrete work (Multiple)
IS 456:2000, IS 10262:2009, IS 383:1970 (Coarse and Fine Aggregate), IS 1786:2008, IS 516:1959, IS 1199:1959, IS 1498:1970 (Steel), IS 4031:1988 (Cement Testing)
B2Approved Drawings List
Reference drawing numbers with revisions (IS 456:2000)
List drawing nos. and latest approved revisions
B3Approved Mix Design
Reference to approved IS 10262 mix design document (IS 10262:2009)
Document ID, grade, w/c ratio, slump, cement type, approval date and approver signature
B4Project Specification
Concrete specification from project contract/design doc (IS 456:2000)
Grade, exposure class, durability requirements, special requirements (if any)
C. C. MATERIALS
C1Cement - Type and Grade
Type of cement (OPC/PPC/PSC) and grade per IS 269/455/1489 (IS 269:2015 (OPC), IS 455:1989 (PPC), IS 1489:1991 (PSC))
Grade 43/53; source and Mill Test Certificate (MTC) records maintained
C2Cement Storage Requirements
Storage conditions per IS 456 Cl. 5.2 (IS 456:2000 Cl. 5.2)
In covered store; max 10 bags high; on raised platform; FIFO rotation; shelf life 3 months max from date of packing; stock rotation recorded
C3Fine Aggregate (Sand) - Source and Grading
Source and compliance with IS 383:1970 grading zone (IS 383:1970, IS 1199:1959 Cl. 3)
Grading Zone II or III; natural or manufactured sand; silt content ≤3% (for fine sand) or ≤5% (coarse sand); testing per IS 2386:1963 Part I
C4Coarse Aggregate (Stone/Gravel) - Source and Grading
Source and compliance with IS 383:1970 grading (IS 383:1970, IS 1199:1959 Cl. 3)
20mm nominal size typical; flakiness index ≤30%; elongation index ≤30%; testing per IS 2386:1963 Part I; all sizes tested before batching commenced
C5Aggregate Testing Frequency
Schedule for regular testing of aggregates (IS 383:1970, IS 1199:1959)
Sieve analysis every 500 tonnes; silt/moisture every 100 tonnes; flakiness/elongation every 1000 tonnes; records maintained with dates
C6Reinforcement Steel - Grade and Type
Steel grade per IS 1786:2008 (High strength deformed bars) (IS 1786:2008, IS 1498:1970)
Grade Fe 500D (primary); diameter per drawings; Mill Certificates (MC) obtained; traceability maintained
C7Steel Storage and Protection
Storage conditions for reinforcement steel (IS 456:2000 Cl. 5.6)
On raised platform (min 300mm height); covered from rain; inspect for rust/damage before use; oiled if stored >6 months; bending at site tested per IS 1608:1995 (bend/rebend test)
C8Water Quality
Water used in concrete mix per IS 456 Cl. 5.4 (IS 456:2000 Cl. 5.4, IS 1199:1959)
Potable water; pH 6-8; salt content <500 mg/litre; chloride <200 mg/litre; sulphate <200 mg/litre; testing done before use
C9Admixtures - Type and Dosage
Chemical admixtures per IS 9103:1999 and approved mix design (IS 9103:1999)
Type (plasticizer/retarder/accelerator/air-entraining); dosage in mL/100kg cement or % by mass; approved mix design reference; batch testing if new source
Showing 17 of 46 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED - REVISE AND RESUBMIT
Prepared By (QC Engineer)
Name / Sign / Date
Signature
Name / Sign / Date
Reviewed By (Senior Engineer)
Name / Sign / Date
Signature
Name / Sign / Date
Site In-charge Acknowledgment
Name / Sign / Date
Signature
Name / Sign / Date