QA/QC  › Bridges  › Bridge Method Statement
Form · QC-BRG-FRM-001

Bridge Method Statement

22 checkpoints across 5 sections. Submitted before construction begins; guides entire project execution
22 Checkpoints
5 Sections
One per project; reviewed and approved before commencement
Contractor, QC Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. CONSTRUCTION METHODOLOGY
A1Foundation construction approach (piling / caisson)
Acceptance: Methodology detailed; equipment specified; sequence documented
Cl. 3.1 — Method per design
OK
NC
NA
HOLD
A2Substructure construction (abutment / pier)
Acceptance: Formwork design; concrete placement; curing protocol
Cl. 4.1 — Phased approach
OK
NC
NA
HOLD
A3Bearing installation methodology
Acceptance: Bearing placement sequence; jacking details; alignment verification
Cl. 5.1 — Installation procedure
OK
NC
NA
HOLD
A4Deck construction (in-situ / precast)
Acceptance: If in-situ: formwork, reinforcement, concrete placement sequence
Cl. 6.1 — Construction type
OK
NC
NA
HOLD
A5Prestressing methodology (if applicable)
Acceptance: Jacking sequence; stressing schedule; monitoring plan
Cl. 7.1 — Stressing procedure
OK
NC
NA
HOLD
A6Testing and commissioning schedule
Acceptance: Proof load test plan; deflection monitoring; bearing tests
Cl. 8.1 — Test execution plan
OK
NC
NA
HOLD
B. QUALITY ASSURANCE STRATEGY
B1Material testing and inspection plan
Acceptance: Steel testing; concrete testing; bearing testing; test frequency and locations
Cl. 9.1 — Material compliance
OK
NC
NA
HOLD
B2QC checklist application and sign-off
Acceptance: QC-BRG-CHK-001 to 004 referenced; sign-off authority identified
Cl. 9.2 — Inspection gates
OK
NC
NA
HOLD
B3Test report documentation
Acceptance: QC-BRG-TST-001 to 003 referenced; testing schedule provided
Cl. 9.3 — Testing compliance
OK
NC
NA
HOLD
B4Third-party / independent inspection
Acceptance: If required: audit frequency; inspection points; authority identified
Cl. 9.4 — External audit
OK
NC
NA
HOLD
C. RESOURCE MANAGEMENT
C1Project team composition
Acceptance: Site Engineer; QC Manager; Safety Officer; Skilled workers
Cl. 10.1 — Qualified personnel
OK
NC
NA
HOLD
C2Construction equipment and machinery
Acceptance: Formwork; cranes; concrete pumps; testing equipment list
Cl. 10.2 — Adequate equipment
OK
NC
NA
HOLD
C3Material supply and logistics
Acceptance: Supply schedule; storage facilities; quality assurance at source
Cl. 10.3 — Procurement plan
OK
NC
NA
HOLD
C4Site facilities and accommodation
Acceptance: Office; testing lab; material storage; safety facilities
Cl. 10.4 — Site management
OK
NC
NA
HOLD
Showing 14 of 22 checkpoints ·
A. CONSTRUCTION METHODOLOGY
A1Foundation construction approach (piling / caisson)
Cl. 3.1 — Method per design (IRC 6)
Methodology detailed; equipment specified; sequence documented
OKNCNAHOLD
A2Substructure construction (abutment / pier)
Cl. 4.1 — Phased approach (IS 456)
Formwork design; concrete placement; curing protocol
OKNCNAHOLD
A3Bearing installation methodology
Cl. 5.1 — Installation procedure (IRC 6)
Bearing placement sequence; jacking details; alignment verification
OKNCNAHOLD
A4Deck construction (in-situ / precast)
Cl. 6.1 — Construction type (IS 456)
If in-situ: formwork, reinforcement, concrete placement sequence
OKNCNAHOLD
A5Prestressing methodology (if applicable)
Cl. 7.1 — Stressing procedure (IS 1343)
Jacking sequence; stressing schedule; monitoring plan
OKNCNAHOLD
A6Testing and commissioning schedule
Cl. 8.1 — Test execution plan (IRC 6)
Proof load test plan; deflection monitoring; bearing tests
OKNCNAHOLD
B. QUALITY ASSURANCE STRATEGY
B1Material testing and inspection plan
Cl. 9.1 — Material compliance (IS 456)
Steel testing; concrete testing; bearing testing; test frequency and locations
OKNCNAHOLD
B2QC checklist application and sign-off
Cl. 9.2 — Inspection gates (IRC 6)
QC-BRG-CHK-001 to 004 referenced; sign-off authority identified
OKNCNAHOLD
B3Test report documentation
Cl. 9.3 — Testing compliance (IRC 6)
QC-BRG-TST-001 to 003 referenced; testing schedule provided
OKNCNAHOLD
B4Third-party / independent inspection
Cl. 9.4 — External audit (IRC 6)
If required: audit frequency; inspection points; authority identified
OKNCNAHOLD
C. RESOURCE MANAGEMENT
C1Project team composition
Cl. 10.1 — Qualified personnel (IRC 6)
Site Engineer; QC Manager; Safety Officer; Skilled workers
OKNCNAHOLD
C2Construction equipment and machinery
Cl. 10.2 — Adequate equipment (IRC 6)
Formwork; cranes; concrete pumps; testing equipment list
OKNCNAHOLD
C3Material supply and logistics
Cl. 10.3 — Procurement plan (IS 456)
Supply schedule; storage facilities; quality assurance at source
OKNCNAHOLD
C4Site facilities and accommodation
Cl. 10.4 — Site management (IRC 6)
Office; testing lab; material storage; safety facilities
OKNCNAHOLD
Showing 14 of 22 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED
Method Statement Summary
Name / Sign / Date
Key Construction Phases
Name / Sign / Date
Quality and Safety Strategy
Name / Sign / Date
Risks and Mitigation
Name / Sign / Date
Proposed By
Name / Sign / Date
Reviewed By
Name / Sign / Date
Approved By
Name / Sign / Date