BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVEInfraLens App·Free on Play Store, offline-readyNEW
PMC Risk · Issue · ChangeForce Majeure Event Log

Force Majeure Event Log

log
PMC-RSK-LOG-004·v1.0-beta·⚠ Beta — review before use

Logs all Force Majeure events affecting the project — natural disasters, pandemic, war, strikes, government action. Documents notice, mitigation, time/cost impact + contractual relief.

ReferencesFIDIC Sub-clause 19 / 18 (Force Majeure)Indian Contract Act 1872 — Section 56 (Doctrine of Frustration)Project-specific Contract Force Majeure Clause
Download
📍 When to use this template
  • Each Force Majeure event invoked.
  • Long-duration FM event tracking (COVID, floods).
  • Settlement of FM-attributed claims.
  • Insurance + reinsurance claims for FM.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Event Header6 fields
Event Number
_____________
Date of Event Onset
_____________
Date of Notice (per FIDIC 19.2)
_____________
Event Type (Natural Disaster / Pandemic / War / Strike / Government Action)
_____________
Event Description
_____________
Geographic Scope (Site / Region / National / International)
_____________
2Mitigation Efforts5 fields
Pre-event Mitigation Plans in Place
_____________
Immediate Actions Taken
_____________
Reasonable Steps to Mitigate Impact
_____________
Communication with Stakeholders
_____________
Resource Re-deployment
_____________
3Impact Assessment6 fields
Direct Impact on Activities
_____________
Schedule Delay (Days)
_____________
Cost Impact (Direct + Consequential)
_____________
Resource Impact (Labour / Equipment)
_____________
Material Disruption
_____________
Loss / Damage to Works
_____________
4Contractual Relief6 fields
FIDIC Sub-clause Applicable
_____________
Extension of Time (Days)
_____________
Cost Relief (per Contract)
_____________
Cost Sharing (50/50 typical)
_____________
Insurance Recovery
_____________
Engineer's Determination
_____________
5Resolution5 fields
Event End Date
_____________
Recovery Period
_____________
Return to Normal Operations
_____________
Settlement of Cost Claims
_____________
Lessons Learned
_____________
💡 Sample filled excerpt
Force Majeure Event: COVID-19 Pandemic (2020-2022). Onset: 24-Mar-2020 (India lockdown). Mitigation: WFH for staff, deferred site activities. Impact: 3 months site closure, ₹15 cr cost (labour wages, demobilization). Contractual relief: 90 days EOT + ₹5 cr cost (50-50 share). Insurance: ₹2 cr recovered. Resolution: 30-Jun-2022 (full operations).
⚖ Compliance notes
  • Per FIDIC Sub-clause 19, Force Majeure includes: war, terror, riot, strike, lock-outs, natural catastrophes, lockdowns, government orders.
  • Notice within 14 days of becoming aware of event (FIDIC 19.2).
  • Reasonable mitigation effort required — failure to mitigate may forfeit FM defence.
  • Time + cost relief: time always granted; cost typically shared 50-50 or per contract terms.
  • Indian Contract Act Section 56 (Frustration) applies if FM makes performance impossible.
  • Insurance coverage for FM events (war / terror / political risk) is a separate consideration; standard CAR policies may exclude.

Engineer's Notes — Force Majeure Event Log

Why the Force Majeure Log matters

Force Majeure (FM) events — natural disasters, pandemics, wars, civil unrest, government action, strikes — are events beyond the parties' control that prevent or delay contract performance. Indian construction projects experienced this acutely during COVID-19 (2020-2022), when the entire industry shut down for 8-12 weeks + operated below capacity for 18-24 months.

The Force Majeure Log captures every FM event affecting a project: onset, mitigation, impact, contractual relief, resolution. It is the primary documentation for: - Extension of Time (EOT) claims under FIDIC Sub-clause 8.4 - Cost claims for additional expenses + losses - Frustration defences under Indian Contract Act Sec 56 - Insurance claims under CAR (Contractor's All Risk) + business interruption + political risk policies - Concession Agreement adjustments for PPP projects - Lender forbearance discussions - Termination payment if FM continues > stipulated period

Without disciplined FM logging: - Claims fail for lack of contemporaneous record - EOT denied by Engineer / Authority - Cost relief refused - Disputes escalate to arbitration - Insurance claims rejected

Governed by FIDIC Sub-clauses 19 (1999) / 18 (2017) — Force Majeure provisions; Indian Contract Act 1872 Section 56 — Doctrine of Frustration; project-specific FM clauses + Concession Agreements + state-PWD contracts.

How Force Majeure operates contractually

FIDIC FM definition (Sub-clause 19.1 / 18.1): An event or circumstance which is: - (a) beyond a Party's control - (b) Party could not reasonably have provided against before contract - (c) having arisen, could not reasonably have been avoided / overcome - (d) not substantially attributable to the other Party

Examples (illustrative, FIDIC 19.1): - (i) War, hostilities, invasion, act of foreign enemy - (ii) Rebellion, terrorism, civil war, riot, commotion - (iii) Munitions, explosives, ionising radiation - (iv) Natural catastrophes (earthquake, hurricane, typhoon, volcano) - (v) Strike / lockout by persons other than Contractor's / Subcontractor's personnel - (vi) Government action / inaction

Notice requirement (Sub-clause 19.2): - Affected Party gives notice within 14 days of becoming aware - Identifies the FM event - Identifies obligations affected - Time + cost impact estimate

Mitigation obligation (Sub-clause 19.3): - Both Parties must mitigate effects - Demonstrable mitigation efforts required - Failure to mitigate may forfeit FM relief - Alternative arrangements (resource re-deployment, alternative routes, sub-contracting)

Relief available: - EOT (Extension of Time) for delays caused by FM - Cost relief for some FM events (per Sub-clause 19.4): - Natural catastrophe: cost typically Contractor's risk - War / Civil unrest: cost typically Employer's risk - Government action: typically Employer's risk - Some contracts: 50-50 cost sharing - Termination if FM continues > 84 days (FIDIC default) or contract-specified period

Termination consequences (Sub-clause 19.6): - Released from further performance - Payment for executed work - Cost of demobilisation - Cost of mobilisation rendered useless - Loss of profit on un-executed work (generally not recovered)

Indian Contract Act Section 56 — Frustration: - Contract void if performance becomes impossible OR illegal - Different from FM clause (Section 56 = no contract; FM clause = relief within contract) - Less commonly invoked for construction (FM clauses usually adequate)

COVID-19 example (most significant recent FM): - First wave: March-June 2020. India-wide lockdown. - Site closures (8-12 weeks) - Labour migration crisis - Material supply disruption - All sites: ~90 day delay; EOT typically granted - Cost: shared 50-50 or per contract - Second wave: April-June 2021. Regional lockdowns. - Site operations restricted - Worker housing crisis - Many sub-contractors bankrupted - Recovery: 2022 onward. Supply chain disrupted till mid-2023. - Cement prices up 25%, steel 35% - Worker availability constrained - Productivity 65-75% of pre-COVID till mid-2022

Common Force Majeure log failures

1. Late notice — 14-day deadline missed; FM relief forfeited; cost falls on contractor.

2. Generic notice — "FM event has occurred"; doesn't identify obligations affected; insufficient.

3. No mitigation demonstrated — sat idle during FM; no alternative arrangement attempted; relief denied.

4. Impact not quantified — claim is qualitative; Engineer needs specific days + costs; rejection.

5. Continuous events not separately notified — one FM event log for multi-month event; should be updates.

6. No daily contemporaneous record — site activity log during FM not maintained; claim defence weak.

7. Concurrent delays not separated — Contractor's own delays + FM delays mixed; Engineer can deny FM impact.

8. Insurance not pursued in parallel — FM coverage in CAR / BI policy; not invoked; lost recovery.

9. Cost claim includes ineligible items — loss of profit (not recoverable), opportunity cost; reduces credibility.

10. No correspondence file — emails, letters, meeting notes not preserved; reconstruction at claim time.

11. EOT claim without programme analysis — must show critical path impact (TIA - Time Impact Analysis); without it, EOT denied.

12. Force Majeure declared opportunistically — invoked for routine delays; loses credibility for real FM.

13. No relief for sub-contractors — main contractor pays sub-cons normally during FM; can't recover from employer.

14. Mitigation costs not claimed — additional costs to mitigate FM (alternative sourcing, expediting) ignored.

15. No closure document — FM event ended but log not closed; ambiguity on resumption date.

16. Government action lumped with policy decisions — "increased GST rate" not FM; "lockdown order" is FM; distinction blurred.

17. Risk shift after onset — contract clearly allocates FM risk; party tries to shift later via informal arrangement.

Cross-references

Companion PMC formats: - Claim Log (PMC-RSK-LOG-003) — for FM-related claims - Dispute Register (PMC-RSK-REG-005) — if FM dispute - Risk Register (PMC-RSK-REG-004) - Daily Progress Report (FMT-SIT-016) — contemporaneous record - Weekly Progress Report (PMC-RPT-RPT-009) - Productivity Tracker (PMC-RPT-RPT-007) — productivity loss data

Contractual + legal framework: - FIDIC Red / Yellow / Silver Book 1999 — Sub-clause 19 (Force Majeure) - FIDIC 2017 Editions — Sub-clause 18 (Exceptional Events) — modernised terminology - FIDIC Sub-clause 8.4 — Extension of Time for Completion - FIDIC Sub-clause 20.1 — Contractor's Claims - Indian Contract Act 1872: - Section 32 — Conditional contracts - Section 56 — Doctrine of Frustration - Section 73-75 — Damages + Compensation - CPWD Works Manual 2019 — FM provisions - NHAI / MoRT&H Concession Agreement — Article 21 typically (FM) - PPP Concession Agreements — model FM provisions - Insurance policies: - CAR (Contractor's All Risk) — covers some FM events - Business Interruption — for revenue loss - Political Risk Insurance (PRI) — for sovereign action - Terrorism Insurance — separate cover - SC + HC judgments: Energy Watchdog vs CERC (SC 2017), Halliburton vs Vedanta (SC 2020) — FM jurisprudence - MoF Office Memoranda on COVID-19 FM treatment (2020-2022)