Standardised request for material issue from stores to site / sub-contractor / department. Replaces ad-hoc requests + creates audit trail for consumption.
Indent #1245, 12-May-2026. Item: TMT 12 mm Γ 12 m = 200 nos. Activity: L+5 slab rebar fixing. Approval: Site Engineer. Issued: 200 nos, balance 0. Opening: 350, Closing: 150. Re-order triggered for replenishment.
The Stores Indent is a formal written request from a site execution team to the stores department for materials needed for upcoming work. It transitions an informal request ('we need 50 bags of cement tomorrow') into a documented, traceable demand that flows through proper authorization, stock check, and issue.
Without indents, sites operate on verbal requests β storekeeper issues whatever is asked β no traceability β reconciliation impossible. The indent forms the first link in the procurement-to-consumption chain that later supports billing, audit, and project closeout.
Workflow: 1. Site engineer raises indent β material, quantity, work activity reference, required date 2. Project office reviews β verifies quantity reasonable for the activity; checks against BOQ allocation; approves above threshold 3. Stores checks availability β current stock vs requested quantity 4. Available: issue voucher generated (FMT-STR-003); material delivered 5. Not available: procurement team triggers purchase order to supplier 6. Reorder triggers β if stock below safety level, indent β automatic PR (purchase requisition) β PO
Sequential numbering important for audit trail; project-specific prefix (e.g., PRJ-001-IND-2025-0123) for traceability.
Approval thresholds typical: - Below βΉ50,000: Site engineer - βΉ50,000 - βΉ2 lakh: Project manager - βΉ2 lakh - βΉ10 lakh: Senior PM / Construction manager - Above βΉ10 lakh: Project director / Client approval
1. No indent β verbal requests β material issued without formal indent; reconciliation impossible later.
2. Over-indenting β site engineer indents more than activity requires (safety margin); excess material consumed by misuse / pilferage.
3. No BOQ cross-reference β indent doesn't reference BOQ item / activity code; impossible to verify quantity is appropriate.
4. Approval bypassed β large indents broken into smaller pieces to fit lower approval threshold; circumvention of governance.
5. No safety stock management β reactive ordering causes stock-outs + work stoppages; project schedule slips.
6. Procurement delays β indent raised but PO not placed for days/weeks; site stops waiting for material.
7. No closing reconciliation β indented quantity vs actually consumed not compared; waste/pilferage gaps undetected.
Companion formats: - Stores Inward Register (FMT-STR-009) β material receipt - Issue Voucher (FMT-STR-003) β formal issue from stores - Bin Card (FMT-STR-005) β running stock per material - Material Reconciliation Register (PMC-PRC-REG-009) β periodic reconciliation - Material Returns Note (FMT-STR-004) β surplus / damaged returns
Procurement governance: ISO 9001:2015 Clause 8.4 (control of externally provided processes); contract clauses on material accountability + reconciliation.