BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVEInfraLens App·Free on Play Store, offline-readyNEW
PMC💰 Contract & BillingPerformance Bank Guarantee Tracker

Performance Bank Guarantee Tracker

log
PMC-BIL-LOG-003·v1.0-beta·⚠ Beta — review before use

Tracks Performance Bank Guarantee + ancillary BGs (advance, retention) — issuance, validity, renewal, partial release at completion + DLP, final release at warranty end.

ReferencesFIDIC Sub-clause 4.2 (Performance Security)CPWD Works Manual 2019Project-specific Contract Agreement
Download
📍 When to use this template
  • Pre-contract: BG issuance verification.
  • Periodic renewal tracking (annual + pre-expiry).
  • Substantial completion: partial release per contract.
  • DLP expiry: final release.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1BG Master Record9 fields
BG Type (Performance / Advance / Retention / Maintenance)
_____________
BG Issuing Bank
_____________
BG Number
_____________
BG Amount (₹)
_____________
% of Contract Value
_____________
Issue Date
_____________
Initial Validity (End Date)
_____________
Beneficiary
_____________
Counter-guarantee (if any)
_____________
2Renewal History4 fields
Renewal Date
_____________
Extended Validity Until
_____________
Renewal Reason (Project Extension / DLP / etc.)
_____________
Updated BG Number (if changed)
_____________
3Release Schedule6 fields
Substantial Completion Date
_____________
% Released at Substantial Completion
_____________
Retention BG to Replace Performance BG (Y/N)
_____________
DLP Start + End
_____________
Final Release Date
_____________
BG Discharged to Bank
_____________
4Encashment Risk5 fields
Defects Liability Issues
_____________
Contractor Default Events
_____________
Demand for BG Encashment (if any)
_____________
Bank Notification + Response
_____________
Encashment Date + Amount (if invoked)
_____________
💡 Sample filled excerpt
Performance BG: SBI BG #2026-XXX, ₹4.5 cr (10 % of ₹45 cr contract). Issued 28-Apr-2026, validity 31-Dec-2027. Substantial completion expected: 30-Sep-2027. Schedule: 50 % release at SC, balance at DLP end (30-Sep-2029). No encashment events.
⚖ Compliance notes
  • Performance BG typically 5-10 % of contract value per FIDIC Sub-clause 4.2.
  • BG validity must cover contract + DLP + 60-90 days safety margin.
  • Renewal 30 days before expiry is the contractor's obligation; failure may attract penalty / contract termination.
  • BG is unconditional + payable on demand (typical Indian practice); contractor cannot dispute encashment at bank.
  • Counter-guarantee from contractor's parent / promoter common for high-value contracts.

Engineer's Notes — Performance Bank Guarantee Tracker

Why the Performance BG Tracker matters

Performance Bank Guarantees (PBG) are typically 5-10% of contract value, deposited by the contractor at project start, valid through construction + Defect Liability Period (DLP). For a ₹100 crore project, that's ₹5-10 crore tied up — a significant working capital commitment.

BGs have fixed validity periods (typically 12-36 months at issuance). When the project schedule extends beyond original validity, the BG must be renewed or replaced before expiry. Letting a BG expire = no guarantee = client demands fresh BG immediately + contractor faces working-capital crisis.

The PBG Tracker is the project-level log of every BG: issuing bank, amount, validity start + end, type, beneficiary, expiry date, renewal status, release date.

What the tracker captures

Per-BG entry: - BG instrument number - Issuing bank + branch - Beneficiary (client / employer legal name) - Amount (in figures + words) - BG type (conditional / unconditional / on-demand) - Issue date + validity start + validity end - Days remaining until expiry - Renewal status (Active / Due / Renewed / Expired / Released) - Renewal notice issued date - Renewed BG instrument number - Release / cancellation date

Renewal lead time: - 90 days before expiry: alert PMC - 60 days: contractor formally notifies bank for renewal - 30 days: contractor must have replacement BG instrument ready - 0 days: original BG expires; replacement must be in effect

Release conditions (per contract): - 50% release at substantial completion (typically 12 months post handover) - 50% release at DLP expiry (typically 24-36 months post handover) - Full release: when all defects rectified + client satisfied

Common BG-management issues

1. BG expired before renewal — client invokes for full amount before contractor can secure replacement; financial crisis. 2. Conditional BG — bank refuses to pay on client's invocation; legal disputes; renders BG ineffective. 3. Wrong beneficiary — BG names parent company instead of contractual subsidiary; client cannot invoke. 4. Bank refuses renewal — contractor's financial position deteriorated; bank withdraws BG facility; client demands fresh BG. 5. Currency mismatch — international project BG in foreign currency; rupee depreciation affects amount. 6. No tracker — multiple BGs lost; renewals missed; project credibility damaged. 7. Counter-guarantee complications — contractor's parent guarantees BG to bank; parent's credit affects BG validity. 8. Release delay — substantial completion certificate issued but client doesn't release BG; contractor's funds blocked indefinitely. 9. Mismatched validity — BG validity shorter than contract duration; gap between BG expiry + project completion.

Cross-references

Companion PMC formats: - Performance BG Submission Letter (FMT-TND-015) — original submission record - Contract Amendment Log (PMC-BIL-LOG-004) — for BG-related amendments - Deductions Register (PMC-BIL-REG-002) — BG vs retention coordination - Letter of Award (FMT-TND-014) — original BG terms reference

Legal + regulatory: - Indian Contract Act 1872 — Section 126 (contracts of guarantee) - RBI Master Direction on Letter of Credits + BGs — banking regulations - FIDIC General Conditions — Clause 4.2 (Performance Security) - NHAI / MoRTH / CPWD standard contracts — Indian government-specific PBG terms