BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEW→BidEasy·Government tenders, searchableLIVE→InfraLens App·Free on Play Store, offline-readyNEW→
Formats Β β€ΊΒ Site Execution Β β€ΊΒ Formwork Removal Schedule
Schedule Β· FMT-SIT-024

Formwork Removal Schedule

5 fields across 3 sections. Weekly de-shutter planning + dependency on cube strength + reshoring.
5 Fields
3 Sections
Weekly review
Site Engineer, QC Engineer

Format Preview

S.No.Field / CheckpointReferenceStatus
A. ELEMENT SCHEDULE
A1Element ID + pour date + grade + span
Acceptance: Tabulated
Per project tracker
OK
NC
NA
A2De-shutter date (per IS 456 Table 7)
Acceptance: Per element type
Per code
OK
NC
NA
B. DEPENDENCY
B1Reshoring schedule (for upper-floor slabs)
Acceptance: Per shoring plan
Distribute load to lower floors
OK
NC
NA
B2Cube strength verification before each removal
Acceptance: Test result attached
IS 456 Cl. 16.5 β€” 70% fck for major elements
OK
NC
NA
C. APPROVALS
C1De-shutter permit raised for each element
Acceptance: Permit log
FMT-SIT-022 process
OK
NC
NA
A. ELEMENT SCHEDULE
A1Element ID + pour date + grade + span
Per project tracker
βœ“ Tabulated
OKNCNA
A2De-shutter date (per IS 456 Table 7)
Per code
βœ“ Per element type
OKNCNA
B. DEPENDENCY
B1Reshoring schedule (for upper-floor slabs)
Distribute load to lower floors
βœ“ Per shoring plan
OKNCNA
B2Cube strength verification before each removal
IS 456 Cl. 16.5 β€” 70% fck for major elements
βœ“ Test result attached
OKNCNA
C. APPROVALS
C1De-shutter permit raised for each element
FMT-SIT-022 process
βœ“ Permit log
OKNCNA
Approval / Sign-Off
APPROVED
HOLD β€” REVISIONS REQUIRED
REJECTED
Overall Verdict
Name / Sign / Date
Prepared By β€” Name / Sign
Name / Sign / Date
Reviewed By β€” Name / Sign
Name / Sign / Date
Approved By β€” Name / Sign
Name / Sign / Date
Date & Time
Name / Sign / Date
Remarks
Name / Sign / Date

Engineer's Notes β€” Formwork Removal Schedule

Why the Formwork Removal Schedule matters

Formwork (shuttering) is the temporary structure that supports fresh concrete until it gains sufficient strength to support its own weight. Premature formwork removal causes excessive deflection, surface damage, or in worst cases, structural collapse. Late removal wastes formwork (kept idle longer than needed), delays construction, and increases hire/depreciation costs.

IS 456:2000 Clause 11.3 specifies the minimum formwork stripping times based on concrete grade + ambient temperature + structural element type. The Formwork Removal Schedule tracks each pour against these mandatory minimums + actual planned removal date.

IS 456 stripping times (Clause 11.3)

For ordinary Portland cement (OPC) concrete at 15Β°C ambient temperature minimum:

| Element | Minimum stripping time | |---|---| | Vertical formwork (column / wall / beam side) | 16-24 hours | | Soffit formwork β€” slabs (props left) | 3 days | | Soffit formwork β€” beams (props left) | 7 days | | Props to slabs (spans ≀ 4.5 m) | 7 days | | Props to slabs (spans > 4.5 m) | 14 days | | Props to beams (spans ≀ 6 m) | 14 days | | Props to beams (spans > 6 m) | 21 days | | Cantilevers β€” main soffit + supports | 28 days |

Adjustments for low temperature: time increases proportionally below 15Β°C. Multiply by 2 at 5Β°C; 3 at 0Β°C.

For PPC / blended cements: add 1-3 days to all minimums (slower strength gain).

For high-strength / accelerated concrete: may be reduced; document with cube test data + design approval.

How to use this schedule on site

Per-pour entry: - Pour ID (column / slab / beam reference) - Pour date + concrete grade - Ambient temperature category - Formwork type (column / wall / slab soffit / props / beam) - IS 456 minimum stripping time (auto-calculated from above) - Cube test results (28-day not waited for; use 7-day if available) - Actual stripping date - Sign-off: PMC engineer + contractor + structural engineer (for cantilevers + premium projects)

Use of cube test for early removal: per IS 456 Cl. 11.3.1, if cube tested at intermediate age shows the concrete has achieved 70% of design strength, early stripping is permitted. Cube test certificate must be attached to the schedule.

Backpropping: even when soffit forms are removed, backprops at strategic spacing are typically retained for additional 7-14 days to support live loads during subsequent floor construction.

Sequence for multi-storey buildings: typically 3-floor cycle β€” current pour at top, backprops 1-2 floors below, formwork fully removed 3 floors below. Sequential strip + relocate.

Common formwork failures this prevents

1. Early stripping cantilever β€” premature stripping of cantilever soffit (before 28 days) is the #1 cause of structural cracking in cantilever balconies + chajjas. The schedule's mandatory 28-day timer prevents this.

2. Premature column stripping β€” vertical column form stripped within 4-8 hours causes surface honeycomb + dimensional loss. Minimum 16-24 hours mandatory.

3. No cube test before early stripping β€” stripping early without verifying concrete strength = guesswork. Mandate cube test + 70% strength verification before any deviation from IS 456 minimums.

4. Insufficient backpropping β€” full formwork removed; floor above poured; live load causes excessive deflection on the unrepaired floor below. Backpropping schedule is critical for multi-storey work.

5. No temperature compensation β€” winter pours stripped per summer schedule cause early-age cracking due to inadequate strength gain. Always adjust for ambient.

6. No formwork inventory tracking β€” formwork not returned to stores promptly; lost / damaged not replaced; costs accumulate.

7. No supervisor sign-off β€” stripping decisions left to crew foreman. Mandate engineer-level sign-off for all stripping events.

Cross-references

Codes: - IS 456:2000 β€” Plain and Reinforced Concrete (the primary; Clause 11.3 on formwork) - IS 14687:1999 β€” Falsework for Concrete Structures β€” Guidelines (for formwork design) - IS 4990:2011 β€” Plywood for Concrete Shuttering Work β€” Specification - IS 10262:2019 β€” Concrete Mix Design (strength gain curves) - IS 516 Part 1 Sec 1:2021 β€” Cube compressive strength test

Companion formats: - Daily Concrete Pour Register (FMT-SIT-015) β€” pour-by-pour log - Curing Register (FMT-SIT-025) β€” companion curing tracker - Cube test register (QC-CON-REG) β€” strength data for early-stripping decisions

More related