BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVEInfraLens App·Free on Play Store, offline-readyNEW
Formats  › Site Execution  › De-shuttering Permit
Form · FMT-SIT-022

De-shuttering Permit

9 fields across 3 sections. Mandatory permit before formwork removal — premature removal = structural failure risk.
9 Fields
3 Sections
Per element
QC Engineer, Consultant

Format Preview

S.No.Field / CheckpointReferenceStatus
A. ELEMENT + POUR DETAILS
A1Element ID + pour date + curing days completed
Acceptance: Documented
Per IS 456 Table 7
OK
NC
NA
A2Grade + characteristic strength achieved (cube test 7-day / 14-day)
Acceptance: Strength data attached
Per IS 456 Cl. 16.5
OK
NC
NA
B. DE-SHUTTERING TIMINGS (IS 456 TABLE 7)
B1Side formwork (column, beam side) — 16-24 hrs
Acceptance: Per code
IS 456 Table 7
OK
NC
NA
B2Slab soffit (≤ 6m span) — 14 days
Acceptance: Strength verified
Cube strength ≥ 50% fck
OK
NC
NA
B3Slab soffit (> 6m span) — 21 days
Acceptance: Strength verified
Cube strength ≥ 70% fck
OK
NC
NA
B4Beam soffit (≤ 6m span) — 14 days; (> 6m) — 21 days
Acceptance: Per code
IS 456 Table 7
OK
NC
NA
B5Cantilever — 28 days minimum
Acceptance: Per code
IS 456 Table 7
OK
NC
NA
C. APPROVAL
C1Strength verified vs required + visual inspection
Acceptance: Approved by QC + consultant
No surface defects after removal
OK
NC
NA
C2Permit to de-shutter issued
Acceptance: Permit number assigned
Triple sign
OK
NC
NA
A. ELEMENT + POUR DETAILS
A1Element ID + pour date + curing days completed
Per IS 456 Table 7
Documented
OKNCNA
A2Grade + characteristic strength achieved (cube test 7-day / 14-day)
Per IS 456 Cl. 16.5
Strength data attached
OKNCNA
B. DE-SHUTTERING TIMINGS (IS 456 TABLE 7)
B1Side formwork (column, beam side) — 16-24 hrs
IS 456 Table 7
Per code
OKNCNA
B2Slab soffit (≤ 6m span) — 14 days
Cube strength ≥ 50% fck
Strength verified
OKNCNA
B3Slab soffit (> 6m span) — 21 days
Cube strength ≥ 70% fck
Strength verified
OKNCNA
B4Beam soffit (≤ 6m span) — 14 days; (> 6m) — 21 days
IS 456 Table 7
Per code
OKNCNA
B5Cantilever — 28 days minimum
IS 456 Table 7
Per code
OKNCNA
C. APPROVAL
C1Strength verified vs required + visual inspection
No surface defects after removal
Approved by QC + consultant
OKNCNA
C2Permit to de-shutter issued
Triple sign
Permit number assigned
OKNCNA
Approval / Sign-Off
APPROVED
HOLD — REVISIONS REQUIRED
REJECTED
Overall Verdict
Name / Sign / Date
Prepared By — Name / Sign
Name / Sign / Date
Reviewed By — Name / Sign
Name / Sign / Date
Approved By — Name / Sign
Name / Sign / Date
Date & Time
Name / Sign / Date
Remarks
Name / Sign / Date

Engineer's Notes — De-shuttering Permit

Why the De-shuttering Permit matters

Formwork (shuttering) removal is a structurally critical operation — premature removal causes excessive deflection, surface damage, or structural collapse. IS 456:2000 Clause 11.3 specifies minimum stripping times based on concrete grade, ambient temperature, structural element.

The De-shuttering Permit is the formal site-level authorization. Before any formwork strip: 1. Site engineer verifies concrete age vs minimum stripping time 2. Cube test results reviewed (if early stripping requested) 3. Backpropping arrangement verified 4. PMC + structural consultant signature obtained 5. Permit issued; only then crew authorized to strip

Without permit discipline, individual workers / supervisors strip on judgement; collapse incidents result. For multi-storey buildings + cantilevers, mandatory permit prevents 100% of premature-stripping incidents.

Standard de-shuttering permit

Permit content: - Project + member reference (Column C-15 / Slab S-4 / Beam B-12) - Concrete grade + ambient temperature - Pour date + age in days at proposed stripping - IS 456 minimum stripping time per element (cross-reference table) - Cube test reference + 7-day / 28-day strength results - Backpropping plan for multi-storey works - Approval: site engineer + PMC + (for cantilevers) structural consultant - Strip date + crew supervisor + sign-off

IS 456 minimum stripping times (15°C+ ambient, OPC concrete): - Vertical formwork (column, wall, beam side): 16-24 hours - Slab soffit (props left): 3 days - Beam soffit (props left): 7 days - Slab props (≤ 4.5 m span): 7 days - Beam props (≤ 6 m span): 14 days - Cantilever soffit + supports: 28 days

For early stripping: cube test must show ≥ 70% of design strength + structural consultant approval.

Common de-shuttering failures

1. Premature stripping — formwork removed before IS 456 minimum age; cracking + deflection. 2. No cube test for early stripping — assumption of strength without verification. 3. No backpropping — slab stripped while floor above is being poured; excessive deflection. 4. Cantilever stripped early — most catastrophic failure mode; minimum 28 days for cantilevers absolute. 5. Cold weather not compensated — winter pour stripped per summer schedule; strength inadequate. 6. PPC concrete treated as OPC — PPC needs longer curing + stripping time. 7. No engineer sign-off — strip decision left to crew foreman; no accountability. 8. Visual inspection only — no measurement of deflection / cracking immediately post-strip.

Cross-references

Companion formats: - Formwork Removal Schedule (FMT-SIT-024) — schedule planning - Daily Concrete Pour Register (FMT-SIT-015) — pour records - Curing Register (FMT-SIT-025) — curing duration - Cube test register (cross-reference)

Codes: - IS 456:2000 — RCC code; Clause 11.3 (formwork) - IS 14687:1999 — Falsework for Concrete Structures - IS 4990:2011 — Plywood for Concrete Shuttering - IS 516 Part 1 Sec 1:2021 — Cube compressive strength

More related